How to Score a Risk Assessment
Learn how to score a risk assessment: rate likelihood and severity, multiply them into a risk score, rank hazards by priority, and track residual risk after controls.
Contents
Scoring a risk assessment means giving each hazard a likelihood rating and a severity rating, then combining the two into a risk score that shows where to act first. A risk matrix turns those two ratings into a single number or band, and the result sets the priority ranking of hazards. The page explains the calculation and how control measures change the score you record.
Rating likelihood and severity
Every hazard gets two separate ratings before any score is calculated. The likelihood rating describes how probable the harm is, and the severity rating describes how bad the harm would be. Teams set simple scales, such as low, medium and high, and write down what each level means. Clear definitions keep two assessors from rating the same hazard differently.
Calculating the risk score
Risk score calculation multiplies the likelihood rating by the severity rating when both use numbers. A scale of one to five for each gives a score from one to twenty-five, and the risk matrix shows where that score falls. A hazard rated high on severity and low on likelihood can land in the same band as the reverse. Decide in advance how your scale handles that difference so the ranking stays consistent.
Ranking hazards and recording residual risk
Priority ranking of hazards follows the score, so the highest scores are addressed first. Each control measure chosen for a hazard changes one or both ratings, and the new figure is the residual risk. Record the original score, the controls, and the residual score together so the reasoning stays visible. A reassessment is needed whenever a control fails or the task changes.
Questions About Risk Assessment Scoring
What is a risk matrix used for?
A risk matrix places the likelihood rating and the severity rating on two axes and shows the resulting risk score in a grid. The grid lets a team compare hazards of different kinds on one scale. It also makes the agreed thresholds visible, so a score above a set line needs action.
Should likelihood or severity count more?
Neither rating outweighs the other in the basic calculation, because the risk score is the product of the two. Severity matters more when a single event could cause grave harm even at low likelihood. Your scale should state how such a hazard is raised above its raw score.
What is residual risk in a risk assessment?
Residual risk is the score left after control measures are applied to a hazard. It is not the same as the original score, so record both figures side by side. If the residual score stays above your threshold, further controls are needed before the task proceeds.
How do control measures change the score?
Control measures change the score by lowering the likelihood rating, the severity rating, or both. A guard that prevents contact with a moving part lowers likelihood, while a weaker force lowers severity. Rate the hazard again after the control is in place, and note which rating moved.